Jack-up System
The jacking-up system is a mechanism used to correct slight tilting of a building caused by differential settlement. Each column of the structure is individually lifted using jacks, and steel plates are inserted to adjust and restore the building's level alignment.
Impact of Constructing a Basement
The central main building of the terminal, which is one of the most prominent structures at the airport, contains a large basement. To construct this basement, it was necessary to excavate soil. However, since the weight of the building was expected to be lighter than the weight of the removed soil, iron ore was placed beneath the main building as ballast to compensate for the difference. Even so, the central main building remains slightly lighter than the surrounding sections. As a result, the central main building has settled less than the surrounding areas, causing a slight incline between the main building and the side wings. To correct this, jacking-up was performed to level the floor.
Automatic Monitoring System
The first terminal building has 900 columns, and the settlement of each column is measured using an automatic monitoring system. Based on this data, the columns that need jacking-up are identified, and operations are carried out accordingly.
Regular Jacking-up Operations
Currently, as ground settlement has gradually stabilized, differential settlement has also decreased. The resulting tilt is now so slight that it is no longer visible to the naked eye. However, jacking-up operations are still carried out every few years as a precaution.

Basic concept of the jack-up system 1

Basic concept of the jack-up system 2

Measures against unequal settlement under the passenger terminal (as of December 2007)

How the pillar under the passenger terminal is jacked up

Other Various Countermeasures
Countermeasures other than Jacking-up
If the overall weight of the island remains uniform, it helps minimize the potential for differences in ground settlement.
Therefore, in addition to jacking-up, Kansai International Airport implemented the following countermeasures during the initial construction phase.
Specific Measures
| Raft foundation | A construction method in which a concrete foundation is placed directly on the ground. This method has the characteristic of allowing the entire structure to settle uniformly in the event of differential settlement. |
|---|---|
| Compaction of the reclaimed layer | Ground compaction was carried out on the 30-meter-deep reclaimed ground to prevent compression during earthquakes. |
| Adjusting the balance through soil removal | To minimize the load difference between the building and the surrounding ground, soil volume was adjusted as necessary. |
As a result of these comprehensive countermeasures, the settlement on Phase 1 island is now primarily attributed to the deep and uniform subsidence of the diluvial layer.
As a result, differential settlement causing operational issues has been minimal at essential facilities such as runways and taxiways.